Georgia hashes out plan to let data centers build their own clean…

Big companies have spent years pushing Georgia to let them find and pay for new clean energy to add to the grid, in the hopes that they could then get data centers and other power-hungry facilities online faster.

Now, that concept is tantalizingly close to becoming a reality, with regulators, utility Georgia Power, and others hammering out the details of a program that could be finalized sometime next year. If approved, the framework could not only benefit companies but also reduce the need for a massive buildout of gas-fired plants that Georgia Power is planning to satiate the artificial intelligence boom.

Today, utilities are responsible for bringing the vast majority of new power projects online in the state. But over the past two years, the Clean Energy Buyers Association has negotiated to secure a commitment from Georgia Power that will, for the first time, allow commercial and industrial customers to bring clean energy projects to the utility’s system,” said Katie Southworth, the deputy director for market and policy innovation in the South and Southeast at the trade group, which includes major hyperscalers like Amazon, Google, Meta, and Microsoft.

The CIR option isn’t a done deal yet. Once Georgia Power, the Public Service Commission, and others work out how the program will function, the utility will file a final version in a separate docket next year.

And the plan put forth by Georgia Power this summer lacks some key features that data center companies want. A big point of contention is that it doesn’t credit the solar and batteries that customers procure as a way to meet future peaks in power demand — the same peaks Georgia Power uses to justify its gas-plant buildout.

But as it stands, CEBA sees the approved CIR framework as a meaningful step toward the bring-your-own clean energy’ model,” Southworth said — a model that goes by the catchy acronym BYONCE in clean-energy social media circles.

Opening up the playing field for clean energy

The CIR option is technically an addition to Georgia Power’s existing Clean and Renewable Energy Subscription (CARES) program, which requires the utility to secure up to 4 gigawatts of new renewable resources by 2035. CARES is a more standard green tariff” program that leaves the utility in control of contracting for resources and making them available to customers under set terms, Southworth explained.

Under the CIR option, by contrast, large customers will be able to seek out their own projects directly with a developer and the utility. Georgia Power will analyze the projects and subject them to tests to establish whether they are cost-effective. Once projects are approved by Georgia Power, built, and online, customers can take credit for the power generated, both on their energy bills and in the form of renewable energy certificates. Georgia Power’s current plan allows the procurement of up to 3 gigawatts of customer-identified resources through 2035.

Letting big companies contract their own clean power is far from a new idea. Since 2014, corporate clean-energy procurements have surpassed 100 gigawatts in the United States, equal to 41% of all clean energy added to the nation’s grid over that time, according to CEBA. Tech giants have made up the lion’s share of that growth and have continued to add more capacity in 2025, despite the headwinds created by the Trump administration and Republicans in Congress.

But most of that investment has happened in parts of the country that operate under competitive energy markets, in which independent developers can build power plants and solar, wind, and battery farms. The Southeast lacks these markets, leaving large, vertically integrated utilities like Georgia Power in control of what gets built. Perhaps not coincidentally, Southeast utilities also have some of the country’s biggest gas-plant expansion plans.

A lot of clean energy projects could use a boost from power-hungry companies. According to the latest data from the Southern Energy Renewable Association trade group, more than 20 gigawatts of solar, battery, and hybrid solar-battery projects are now seeking grid interconnection in Georgia.

The idea that a large customer can buy down the cost of a clean energy resource to make sure it’s brought onto the grid to benefit them and everybody else, because that’s of value to them — that’s theoretically a great concept,” said Jennifer Whitfield, senior attorney at the Southern Environmental Law Center, a nonprofit that’s pushing Georgia regulators to find cleaner, lower-cost alternatives to Georgia Power’s proposed gas-plant expansion. We’re very supportive of the process because it has the potential to be a great asset to everyone else on the grid.”

Isabella Ariza, staff attorney at the Sierra Club’s Beyond Coal Campaign, said CEBA deserves credit for working to secure this option for big customers in Georgia. In fact, she identified it as one of the rare bright spots offsetting a series of decisions from Georgia Power and the Public Service Commission that environmental and consumer advocates fear will raise energy costs and climate pollution.

Great Job Jeff St. John & the Team @ Canary Media Source link for sharing this story.

#FROUSA #HillCountryNews #NewBraunfels #ComalCounty #LocalVoices #IndependentMedia

Felicia Ray Owens
Felicia Ray Owenshttps://feliciarayowens.com
Writer, founder, and civic voice using storytelling, lived experience, and practical insight to help people find balance, clarity, and purpose in their everyday lives.

Latest articles

spot_img

Related articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Leave the field below empty!

spot_img
Secret Link